← EXPLODED VIEWP04

COMPONENT TECHNICAL DOSSIER

One-Hand Closure

The closure is intended to open with one thumb, remain attached and move clear of the nose and cheek.

PRE-INDUSTRIAL R2TETHERED CLOSURE
Technical architecture of the tethered closure
P04 · REFERENCE CONFIGURATION
22registered technical fields
12engineering disciplines
6basis / calculated / measured
6targets to be demonstrated
10fields requiring evidence

01 · PRINCIPLE & RATIONALE

Intended function
and associated requirement.

PRINCIPLE

The closure is intended to open with one thumb, remain attached and move clear of the nose and cheek.

WHY IT IS INCLUDED

The bottle can be opened, used and closed with one hand; the lid cannot fall away, become lost or obstruct the face.

DETAILED DESCRIPTION

Opens with the thumb, remains clear of the face and closes through a dual seal. An integral hinge, an approximately 170° stop and a dual plug-and-land seal operate as one dimensional stack. Opening force, hinge endurance and 24-hour leak tightness are targets; the closure is not approved until tolerance stack-up and testing are complete.

02 · TECHNOLOGY STACK

Technologies, roles
and approval gates.

T-01

Integral tethered hinge

Role
Keeps the lid attached throughout use.
Why
Eliminates loose parts and enables one-thumb operation.
Approval gate
Force-displacement and cycling at 4/23/40 °C.
T-02

~170° kinematic stop

Role
Moves the lid clear of the face.
Why
Improves ergonomics without a second component.
Approval gate
Human factors and tolerance stack-up.
T-03

Dual plug-and-land seal

Role
Separates the primary seal from the seating surface.
Why
Reduces sensitivity to ovalisation and particles.
Approval gate
24-hour leak, pressure decay and drop.

03 · ARCHITECTURE

Function, material
and interfaces.

An integral hinge, an approximately 170° stop and a dual plug-and-land seal operate as one dimensional stack.

MATERIALDuctile PHBH grade to be qualified
CANDIDATE PROCESSInjection moulding · integral hinge
INTERFACES
  • 42 mm mouth
  • FlowCrown
  • tamper-evident ring
FUNCTIONAL ARCHITECTURE
  1. 01Integral tether
  2. 02Stop clear of the face
  3. 03Dual plug-and-land seal
  4. 04Tactile and audible feedback

04 · MASTER PARAMETER REGISTER

Everything to be defined,
measured or certified.

A field without evidence is never filled with an invented number: it remains “To be determined”, together with the method required to close it. This is what makes the technical record verifiable.

DESIGN BASISTARGETCALCULATED / MEASUREDTO BE VALIDATEDCERTIFICATION REQUIRED
01Identification & function3 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-001Assembly codeIDP04—To be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testDESIGN BASIS
P04-002DesignationNAMEOne-Hand Closure—To be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testDESIGN BASIS
P04-X001Intended useUSETo be determined—To be definedFull use cycleDesign review + user studyTO BE VALIDATED
02Risk & maturity2 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-003Architecture revisionREVR2—To be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testDESIGN BASIS
P04-004Technology readinessTRL2–3levelTo be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testTO BE VALIDATED
03Food contact2 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-005Declaration of ComplianceDoCrequireddocumentTo be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testCERTIFICATION REQUIRED
P04-X007Overall and specific migrationMIGTo be determinedmg/kgApplicable limitsSimulant/time/temperatureAccredited methodsTO BE VALIDATED
04Quality control3 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-006Lot traceabilityLOT100%To be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testTARGET
P04-014Opening/closing feedbackCLICKpresent—To be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testTARGET
P04-X006Process capabilityCpkTo be determined—Target to be definedCritical CTQSPC ≥30 samplesTO BE VALIDATED
05Geometry & metrology2 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-007Clear mouth openingDmouth42mmTo be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testDESIGN BASIS
P04-X002Nominal massmTo be determinedgTo be defined23 °C / 50% RHBalance 0.001 gTO BE VALIDATED
06Kinematics / sealing / barrier3 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-008Opening angleαopen≈170°To be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testTARGET
P04-009Thumb opening forceFopen10–18NTo be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testTARGET
P04-010Seal systemSEALplug + land—To be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testDESIGN BASIS
07Durability & reliability2 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-011Minimum hinge cyclesNhinge≥20cyclesTo be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testTARGET
P04-012Inverted leak testtleak24h0 leaks4 °C and 23 °CLeak testTARGET
08Assembly1 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-013Metal parts or loose gasketsnsep0partsTo be defined23 °C / 50% RH unless notedCAD, CAE or dedicated testDESIGN BASIS
09Material1 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-X003Commercial grade and supplierGRADETo be determined—Qualified gradeProduction lotCoA + traceabilityTO BE VALIDATED
10Thermal properties1 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-X004Service-temperature rangeTserviceTo be determined°CTo be definedUse and transportClimate chamberTO BE VALIDATED
11Mechanical properties1 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-X005Drop resistanceHdropTo be determinedmTo be definedDefined orientationsInstrumented drop testTO BE VALIDATED
12Recyclability1 PARAMETERS
IDParameterSymbolValueUnitToleranceConditionMethodStatus
P04-X008Territory-specific end-of-life routeEOLTo be determined—Country/area definedComplete assemblyInfrastructure mappingTO BE VALIDATED

05 · INDUSTRIALISATION

From material
to final inspection.

INPUT

Qualified material

Ductile PHBH grade to be qualified

FORMING

Process within window

Injection moulding · integral hinge

INTEGRATION

Controlled interfaces

42 mm mouth · FlowCrown · tamper-evident ring

RELEASE

CTQ + traceability

Injection moulding, neck assembly and torque/leak control must be separated from filling. Hinge material performance is the principal risk.

06 · DVP&R

A function is approved
only after passing its test.

TestRequirementRiskMethodConditionSamplesAcceptanceOutput
DVP-04Filled-bottle dropBreakage/leakDrop1 m; water 4 °C; base/side/cap600 leaks; 0 loose partsFailure map
DVP-07Closure sealingLeakInverted leak4 °C and 23 °C; 24 h300 leaksLeak report
DVP-08Opening and hingeForce/fatigueForce-displacement + cyclingDry/wet3010–18 N; ≥20 cyclesCurves + failures
DVP-12Food contactMigration/NIASOverall/specific migrationCold-fill water use3 lotsApplicable regulatory complianceSigned report

07 · FAILURE MODES

Failure modes,
causes and controls.

R-01

Body brittleness

EffectBreakage/leak

CausePHA thermal window

ControlDSC/TGA, rheology, process DOE

RPN 315DVP-02/04
R-02

Non-uniform walls

EffectBuckling/drop failure

CauseAsymmetric geometry

ControlBlow-moulding CAE + micro-CT

RPN 336DVP-02/03
R-03

AeroSkin detachment

EffectLoss of function/loose part

CauseInsufficient seal

ControlPeel, thermal cycling and drop

RPN 280DVP-04/05

08 · EVIDENCE POLICY

Traceability
for every parameter.

The design avoids metal parts and loose gaskets. The ductile PHA grade selected for the hinge must remain compatible with the body and the chosen end-of-life route.

This page is the technical register for the R2 configuration. It separates design values, targets, calculations, measurements and certifications. Open fields identify the exact test or document required to close them.

← P03ThermoSnow IndicatorMAPExploded viewP05 →Reversible FlowCrown